SyntropixSYNTROPIXSolutions
IDP · project status

IDP
delivery status.

Intake is operating for established scope. The next releases depend on focused defect fixes, QA evidence and Business acceptance.

i
No single approved IDP go-live date.

AMAC PDF: week of October 5, conditional. Hamaspik: second week of October, tentative. Illinois BCBS: end of October, target. Other releases remain undated.

01 / At a glance

What matters now

Confirmed progress

Processing restored

Hamaspik’s two-case smoke test worked. AMAC PDF five-point matching testing passed; exception coverage remains open.

Current priority

Finish focused QA

Correct and retest AMAC PDF exceptions, complete Hamaspik regression, and clear Lifeline Excel’s mapping/refresh blocker.

Business acceptance

Close the handoffs

AMAC Excel findings need a disposition. Illinois needs an approved requirements baseline and dated test plan.

Evidence quality

Refresh the baseline

Reconcile duplicate treatment and reporting refresh. DocuGate phase completion and older payer priorities need current owner confirmation.

02 / Release readiness

Payer milestones with variant-specific gates

Payer milestones across the four delivery workstreams, with separate release decisions
Payer / variantIntake Business — RequirementsDevelopmentQAIntake Business — UATRelease decision / window
HamaspikActive scope in validationChange available for QARegression in progress; October 6 targetNot passed; October 7–8 targetSecond week of October · tentative
AMAC — PDFException scope requires acceptanceException correction in progressMatching passed; exception retest October 2 targetNot passed; early next week targetWeek of October 5 · conditional
AMAC — ExcelReconcile Business findingsFix disposition unconfirmedSecond pass needed after fixesFindings unresolvedNo approved date
Lifeline — ExcelMapping expectations under reviewMapping / refresh investigationPausedNot reachedNo approved date
Lifeline — PDFVariant scope needs confirmationReported ready September 22Start / pass not confirmedNot confirmedNo approved date
Illinois BCBSReview October 5 · targetAfter approved baseline; date unconfirmedNot confirmedNot confirmedEnd of October · target
HealthfirstEstablished scope; timing decision openDurable attachment correction unconfirmedAdditional fix validation neededOperating scope; new-change acceptance unconfirmedOperating; no new release date
Alignment2027 sample pendingDuplicate fix QA reported underwayDisposition unconfirmedAcceptance unconfirmedJanuary 1 change effective date; release not approved
MeridianDiscovery disposition needs refreshNot confirmedNot confirmedNot confirmedNo verified date
VillageCareMAXOlder baseline; scope needs confirmationNot confirmedNot confirmedNot confirmedNo verified date
HealthPlus / AmerigroupOlder baseline; scope needs confirmationNot confirmedNot confirmedNot confirmedNo verified date

GREEN · operating / on track   YELLOW · in progress / watch   RED · blocked

03 / Operating view

Four workstreams. Payer-specific milestones.

YELLOW · Baseline approval in progressLatest reviewed evidence · October 1

Intake Business — Requirements

Kerin Vansickle / Tiffany Parrish / Gina Sicker; Inosi supports requirements translation

Illinois requirements are being revised for Business review. AMAC Excel findings need reconciliation. Older payer discovery and future Alignment samples need current confirmation.

Gate / decision
Business approval of each payer’s requirements.
Next action
Complete the Illinois review and confirm the open payer requirements and acceptance criteria.
Checkpoint
Illinois review October 5 · target; other dates unconfirmed
Back to workstreams ↑
RED · Active corrections block downstream gatesLatest reviewed evidence · October 1

Development

Inosi Colavanua / Reynaldo Ricafort; Salesforce owners for platform dependencies

AMAC PDF exception correction and Lifeline Excel mapping/account-refresh investigation remain open. AMAC Excel fix scope awaits the reconciled Business findings.

Gate / decision
Delivered corrections with evidence that the intended paths behave correctly.
Next action
Confirm the correction delivery and variant-specific scope before QA resumes or retests.
Checkpoint
AMAC PDF October 1; Lifeline Excel October 2 · targets, not confirmed deliveries
Back to workstreams ↑
RED · Focused validation in progress / blockedLatest reviewed evidence · October 1

QA

Suman Reddy

Hamaspik processing and its two-case smoke test were reported successful; regression remains open. AMAC PDF matching passed but exception coverage is blocked. Lifeline Excel QA is paused.

Gate / decision
A separate documented QA disposition for every payer variant.
Next action
Retest AMAC PDF exceptions, complete Hamaspik regression and resume Lifeline Excel only after the blocker clears.
Checkpoint
AMAC PDF retest October 2; Hamaspik QA October 6 · targets
Back to workstreams ↑
YELLOW · Acceptance pending / findings openLatest reviewed evidence · October 1

Intake Business — UAT

Kerin Vansickle / designated Intake Business reviewers

AMAC Excel UAT findings have not been closed. Hamaspik and AMAC PDF Business acceptance remain conditional on QA handoff; release approval remains pending.

Gate / decision
Business acceptance by payer and variant, followed by a distinct production release decision.
Next action
Reconcile AMAC Excel findings and review the same QA ticket/evidence at each handoff.
Checkpoint
AMAC PDF early week of October 5; Hamaspik October 7–8 · conditional targets
Back to workstreams ↑

Payer milestones

Hamaspik · payer milestone

YELLOW · QA in progressConfirmed smoke-test report · October 1

Hamaspik

Suman Reddy / Inosi Colavanua / Kerin Vansickle / Mary Graves

Test files are processing again. Suman reported a successful two-case smoke test; focused scenarios and regression remain open.

Gate / decision
Scenario and regression evidence, then Business UAT acceptance. Historical remediation disposition also needs confirmation.
Next action
Suman finishes QA and records evidence; Kerin reviews the same ticket after handoff.
Checkpoint
QA October 6; UAT October 7–8 · targets
Release window
Second week of October · tentative, subject to QA and UAT
Back to workstreams ↑

AMAC / 900 MLT · payer milestone

RED · Exception defect blocks handoffConfirmed matching pass + open defect · October 1

900 MLT · AMAC PDF

Reynaldo Ricafort / Inosi Colavanua / Suman Reddy / Kerin Vansickle

Five-point matching passed. A disenrollment exception defect remains open; Reynaldo began the correction during the call.

Gate / decision
Correction, exception retest and formal QA-to-UAT handoff.
Next action
Reynaldo delivers the correction; Suman retests, then hands the ticket to Kerin if QA passes.
Checkpoint
Fix October 1; retest October 2; UAT early October 5 week · targets
Release window
Week of October 5 · conditional on passes and approval
Back to workstreams ↑
YELLOW · UAT findings unresolvedConfirmed unresolved review · October 1

900 MLT · AMAC Excel

Kerin Vansickle / Inosi Colavanua / Reynaldo Ricafort / Suman Reddy

Kerin recalled earlier UAT findings but could not confirm whether the fixes were completed. No UAT pass was given. The current findings are to be reconciled in DE-1532.

Gate / decision
Exact UAT disposition, fix scope and a second QA pass.
Next action
Kerin consolidates findings; engineering gives a fix date; Suman completes QA before Business retests.
Checkpoint
Owner and retest dates needed; review October 6
Back to workstreams ↑

Lifeline / 900 MLT · payer milestone

RED · QA paused · DE-1626Confirmed blocker · October 1

900 MLT · Lifeline Excel

Reynaldo Ricafort / Inosi Colavanua / Suman Reddy

The member-case-ID mapping concern and the account-data refresh concern remain under investigation. A change was observed in the Salesforce copy but not in the IDP account; no root cause or verified fix was confirmed.

Gate / decision
Correct source-to-target mapping and reliable account refresh, with retest evidence.
Next action
Reynaldo and Inosi trace both paths and notify Suman when QA can resume. Hamaspik remains the QA priority.
Checkpoint
Correction October 2 · target; QA next week, roughly one week from restart
Back to workstreams ↑
YELLOW · Development reported ready; QA unconfirmedCarry-forward · September 22–24

900 MLT · Lifeline PDF

Reynaldo Ricafort / Suman Reddy / Tiffany Parrish

PDF development was reported ready for QA on September 22. September 24 sequencing put Lifeline PDF after AMAC PDF. Later calls did not establish a separate Lifeline PDF QA pass or start date.

Gate / decision
Confirm the variant-specific scope, test data and QA ticket before reserving capacity.
Next action
Reynaldo and Suman confirm readiness and sequence; Tiffany confirms applicable samples.
Checkpoint
No committed date in reviewed evidence
Back to workstreams ↑

Illinois BCBS · payer milestone

YELLOW · Requirements reviewConfirmed revision in progress · October 1

Illinois BCBS

Inosi Colavanua / Reynaldo Ricafort / Kerin Vansickle / Tiffany Parrish

Inosi received Business feedback and is revising the requirements document. The next review is planned for Monday. Approval of the revised baseline and a dated delivery plan were not confirmed.

Gate / decision
Business-approved requirements followed by dated development, QA and UAT gates.
Next action
Complete the requirements review, resolve remaining decisions, and publish the delivery sequence.
Checkpoint
October 5 review; end-of-October production · target
Release window
End of October · target, not approved release schedule
Back to workstreams ↑

Healthfirst · payer milestone

GREEN · Operating · monitoringConfirmed report · September 24

Healthfirst intake stability

Kerin Vansickle / Gina Sicker / Inosi Colavanua

Five-point matching is active. No new duplicate issue was reported at the last full-team review. One failed attachment was corrected manually; the remaining attachment population was not confirmed.

Gate / decision
Broader filename cleanup and any additional missing attachments still need confirmation.
Next action
Kerin confirms remaining attachment failures; Inosi validates the durable filename correction.
Checkpoint
October 6 stand-up · follow-up target
Back to workstreams ↑
YELLOW · Operating decision openConfirmed timing issue · October 1

Healthfirst · document/file timing

Inosi Colavanua / Kerin Vansickle / Tiffany Parrish

Referral documents can arrive before the later payer file needed for complete contact data. The call raised timing and reconciliation alternatives without approving a revised processing rule.

Gate / decision
Approved handling of late-arriving data, then validation of the chosen approach.
Next action
Hold a focused working session and document the agreed lookup, reconciliation and exception approach.
Checkpoint
Working session not yet dated
Back to workstreams ↑

Alignment · payer milestone

YELLOW · Fix validation unconfirmedCarry-forward · September 24

Alignment · duplicate remediation

Ben / Inosi Colavanua / Kerin Vansickle

A Salesforce defect was assigned to Ben. QA of the changes was reported underway at the last review; completion and historical cleanup were not confirmed.

Gate / decision
Fix validation and a separately confirmed cleanup result.
Next action
Ben and the Salesforce team report QA disposition; Kerin and Inosi confirm remaining cleanup.
Checkpoint
October 6 stand-up · follow-up target
Back to workstreams ↑
YELLOW · Awaiting sample and delivery dateCarry-forward · September 17–24

Alignment · 2027 product change

Kerin Vansickle / Inosi Colavanua / Suman Reddy

Business described a January 1, 2027 product-selection change. The new sample file and a supplier delivery date had not been received as of the last reviewed discussion.

Gate / decision
Representative sample, agreed mapping, development and QA before cutover.
Next action
Kerin obtains the sample and date; Inosi assesses the change; Suman reserves test coverage.
Checkpoint
January 1, 2027 effective date reported; sample delivery unknown
Back to workstreams ↑

Meridian · payer milestone

YELLOW · Sequence needs refreshOlder carry-forward · September 10 / August project baseline

Payer discovery pipeline

Daniel Lonergan / Kerin Vansickle / Tiffany Parrish / Inosi Colavanua

The joint Meridian discovery had not occurred at the September 10 review while Illinois requirements were prioritized. VillageCareMAX and HealthPlus/Amerigroup remain in the older project baseline; current scope and sequencing need owner confirmation.

Gate / decision
Current approved payer sequence and specific requirements, rather than assuming stale tasks are current commitments.
Next action
Reconfirm discovery disposition and priorities after the active release gates are assessed.
Checkpoint
No verified current delivery dates
Back to workstreams ↑

VillageCareMAX · payer milestone

Scope and delivery dates need owner confirmation; listed in the earlier project baseline.

HealthPlus / Amerigroup · payer milestone

Scope and delivery dates need owner confirmation; listed in the earlier project baseline.

Cross-payer dependencies & separate scope

YELLOW · Control operating; residual reconciliation openCarry-forward · September 22–24

Waiver controls & reconciliation

Mary Graves / JM Calderon / Kerin Vansickle; Bill Manley / Justin for source correction

Required-field configuration and the exception path were reported operating. September 24 raised no new intake issue. The remaining exception population and durable source correction were not closed.

Gate / decision
Post-sync evidence and residual exceptions; downstream Billing acceptance remains distinct from intake configuration.
Next action
Owners confirm the remaining population, correction responsibility and durable fix date.
Checkpoint
October 6 stand-up · follow-up target
Back to workstreams ↑
YELLOW · Trend and refresh validation openConfirmed investigation · October 1

Reporting & operational impact

Daniel Lonergan / JM Calderon / Inosi Colavanua / Kerin Vansickle / Gina Sicker / Tiffany Parrish

September authorization trends need reconciliation against duplicate treatment, referral volume and refresh behavior. Earlier Business feedback reported staff capacity benefits, but a validated savings or service-level measure was not established.

Gate / decision
Reliable refresh, consistent denominator and comparable referral/operating baseline.
Next action
JM and Inosi review reporting logic; Business provides a comparable baseline; Daniel coordinates the review.
Checkpoint
October 6 review · planned checkpoint
Back to workstreams ↑
GREEN · Intake close-out reportedCarry-forward · September 24

Locator-code dependency

Inosi Colavanua / JM Calderon / Salesforce team

The IDP stand-up treated the locator item as ready for intake close-out. Historical loads, residual exceptions and downstream API acceptance belong to the separate Bonafide control work.

Gate / decision
Historical loads and downstream API acceptance are tracked under Bonafide.
Next action
Monitor for a new IDP impact; validate downstream completion in the owning workstream.
Checkpoint
Exception-driven monitoring
Back to workstreams ↑
YELLOW · Separate initiative · current phase unverifiedRoadmap September 10; scope reviewed September 22–October 1

DocuGate / Human-in-the-Loop

Amy Fargnoli / Inosi Colavanua / Business leads

Viewer onboarding and later phases were discussed in September. The September 10 roadmap presented external order visibility as a future concept. Later stand-ups did not establish current phase completion, production acceptance or a new external rollout.

Gate / decision
A dated phase update and any active capture, extraction or interface dependency affecting IDP.
Next action
Amy and Inosi confirm current phase, acceptance evidence, feedback and active IDP dependencies.
Checkpoint
No verified current completion or launch date
Back to workstreams ↑
04 / Next checkpoints

The next decisions and evidence

  1. AMAC PDF correction and retest; Lifeline Excel investigation

    Reynaldo / Inosi / Suman · target dates

  2. Illinois requirements review; AMAC PDF UAT if QA passes

    Inosi / Kerin / Tiffany · requirements review; Kerin · PDF UAT after QA

  3. Hamaspik QA target and stand-up reconciliation

    Suman’s QA result; Daniel / JM / Business report review; carry-forward owner updates.

  4. Hamaspik Business UAT and feedback

    Kerin · target, dependent on QA completion

  5. Illinois production target

    Target only; requirements review scheduled October 5.

Verified through October 1, 2026 · 10:32 a.m. Eastern

Full IDP transcripts: September 10, 17, 22, 24, 29 and October 1; DocuGate roadmap: September 10. Strata Transcribed Meetings, project records and email history reviewed through October 1. Meeting cutoff: 10:32 a.m. Eastern. Email cutoff: 3:31 p.m. Eastern.